Construction Planning and Management A critical ratio scheduling Determines the status of each activity Adjusts automatically changes in activity progress Is a dynamic system None of these Determines the status of each activity Adjusts automatically changes in activity progress Is a dynamic system None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The process of incorporating changes and rescheduling or replanning is called Resource levelling Resource smoothening Critical path scheduling Updating Resource levelling Resource smoothening Critical path scheduling Updating ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The main disadvantage of line organization, is All listed here Rigid structure Top level executions over work Extraordinary delay in communications All listed here Rigid structure Top level executions over work Extraordinary delay in communications ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 1000 cum 1500 cum 500 cum 2000 cum 1000 cum 1500 cum 500 cum 2000 cum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The salient feature of functional organization is All listed here Each individual maintains functional efficiency Strict adherence to specifications Separation of planning and design part All listed here Each individual maintains functional efficiency Strict adherence to specifications Separation of planning and design part ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For excavating utility trenches with precise control of depth, the excavation equipment used is None of these Dragline Hoe Shovel None of these Dragline Hoe Shovel ANSWER DOWNLOAD EXAMIANS APP