Construction Planning and Management Crash project duration is obtained by summing the Crash durations for all activities Normal durations for all the activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Crash durations for all activities Normal durations for all the activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Completion of an activity on CPM network diagram, is generally known Event All listed here Connector Node Event All listed here Connector Node ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The direct cost of a project with respect to normal time is Zero Infinite Maximum Minimum Zero Infinite Maximum Minimum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Power stations are generally treated as Heavy construction Electrical construction Industrial construction Light construction Heavy construction Electrical construction Industrial construction Light construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 9 days 8 days 15 days 10 days 9 days 8 days 15 days 10 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Duration Event Constraint Float Duration Event Constraint Float ANSWER DOWNLOAD EXAMIANS APP