Construction Planning and Management Crash project duration is obtained by summing the Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Crash durations for all activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Normal durations for all the activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Crash durations for all activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Normal durations for all the activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The first method invented for planning projects, was Bar chart method Programme Evaluation and Review Technique (PERT) Milestone chart Critical path method (CPM) Bar chart method Programme Evaluation and Review Technique (PERT) Milestone chart Critical path method (CPM) ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For completion of a project, the critical path of the network represents Maximum time Maximum cost Minimum time Minimum cost Maximum time Maximum cost Minimum time Minimum cost ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is 4 3 1 2 4 3 1 2 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the network shown in the given figure, the expected time for the activity 1-2 is 4 2-3 is 7 All listed here 3-4 is 8 1-2 is 4 2-3 is 7 All listed here 3-4 is 8 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Wheeled tractors are replacing crawler tractors because1. Wheeled tractors travel faster.2. Crawler tractors are more expensive.3. Track parts of a crawler wear out quickly.4. Crawler tractors have stick control.of following statements 1, 3 and 4 are correct 1, 2 and 4 are correct 1, 2 and 3 are correct 2, 3 and 4 are correct 1, 3 and 4 are correct 1, 2 and 4 are correct 1, 2 and 3 are correct 2, 3 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP