Construction Planning and Management For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is 4 2 3 1 4 2 3 1 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Wheeled tractors are replacing crawler tractors because 1. Wheeled tractors travel faster. 2. Crawler tractors are more expensive. 3. Track parts of a crawler wear out quickly. 4. Crawler tractors have stick control. of following statements 1, 3 and 4 are correct 1, 2 and 4 are correct 1, 2 and 3 are correct 2, 3 and 4 are correct 1, 3 and 4 are correct 1, 2 and 4 are correct 1, 2 and 3 are correct 2, 3 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A contractor has two options;(l) : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he could invest in either of the two projects should invest in project B should invest in neither of the two projects should invest in project A could invest in either of the two projects should invest in project B should invest in neither of the two projects should invest in project A ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The direct cost of a project with respect to normal time is Infinite Zero Maximum Minimum Infinite Zero Maximum Minimum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A machine costs Rs. 20000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be Rs. 6960 Rs. 3480 Rs. 5220 Rs. 1740 Rs. 6960 Rs. 3480 Rs. 5220 Rs. 1740 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 500 cum 2000 cum 1500 cum 1000 cum 500 cum 2000 cum 1500 cum 1000 cum ANSWER DOWNLOAD EXAMIANS APP