Construction Planning and Management A construction schedule is prepared after collecting Output of labour Output of machinery All listed here Number of operations Output of labour Output of machinery All listed here Number of operations ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following features/factors: 1. Projects are of the non-repetitive type 2. Time required need not be known 3. Time required is known precisely 4. Events have been established for planning 5. Emphasis is given to activities of project PERT is preferred for planning because of 1, 3 and 4 1, 2 and 5 3, 4 and 5 1, 2 and 4 1, 3 and 4 1, 2 and 5 3, 4 and 5 1, 2 and 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The direct cost of a project with respect to normal time is Zero Infinite Maximum Minimum Zero Infinite Maximum Minimum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be 97.7% and 84.1% 2.3% and 84.1% 97.7 % and 15.9% 15.9% and 97.7% 97.7% and 84.1% 2.3% and 84.1% 97.7 % and 15.9% 15.9% and 97.7% ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The first stage of a construction, is Preparation of tender Preparation of estimate Initiation of proposal Survey of the site Preparation of tender Preparation of estimate Initiation of proposal Survey of the site ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations: 1. Drilling 2. Blasting 3. Mucking 4. Placing steel 5. Placing concrete The correct sequence of these operations in tunnel construction is 1, 2, 3, 4, 5 1, 2, 4, 3, 5 1, 3, 2, 4, 5 1, 3, 4, 2, 5 1, 2, 3, 4, 5 1, 2, 4, 3, 5 1, 3, 2, 4, 5 1, 3, 4, 2, 5 ANSWER DOWNLOAD EXAMIANS APP