Construction Planning and Management A construction schedule is prepared after collecting Number of operations Output of machinery All listed here Output of labour Number of operations Output of machinery All listed here Output of labour ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is 19 14 24 None of these 19 14 24 None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Rolling resistance of a wheel depends upon(i) Vehicle load(ii) Grade(iii) Ground conditions Only (i) is correct (i) and (ii) are correct (ii) and (iii) are correct (i) and (iii) are correct Only (i) is correct (i) and (ii) are correct (ii) and (iii) are correct (i) and (iii) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A machine is purchased for Rs. 10,000,00 and has an estimated life of 10 years. The salvage value at the end of 10 years is Rs. 1,50,000. The book value of the machine at the end of 5 years using general straight line method of evaluation of depreciation is Rs. 5,75,000 Rs. 8,50,000 Rs. 6,50,000 Rs. 4,75,000 Rs. 5,75,000 Rs. 8,50,000 Rs. 6,50,000 Rs. 4,75,000 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following surfaces will give highest coefficient of traction while using crawler track tractors? Loose sand Concrete Earth Ice Loose sand Concrete Earth Ice ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The process of incorporating changes and rescheduling or replanning is called Resource levelling Critical path scheduling Updating Resource smoothening Resource levelling Critical path scheduling Updating Resource smoothening ANSWER DOWNLOAD EXAMIANS APP