Construction Planning and Management A construction schedule is prepared after collecting Output of machinery Number of operations All listed here Output of labour Output of machinery Number of operations All listed here Output of labour ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following surfaces will give highest coefficient of traction while using crawler track tractors? Ice Earth Concrete Loose sand Ice Earth Concrete Loose sand ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Preliminary project report for a road project must contain The soil survey, traffic survey, concept design and approximate cost The several alternatives of the project that have been considered The detailed estimated cost based on detailed design The contract documents for inviting tenders The soil survey, traffic survey, concept design and approximate cost The several alternatives of the project that have been considered The detailed estimated cost based on detailed design The contract documents for inviting tenders ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Power stations are generally treated as Light construction Industrial construction Electrical construction Heavy construction Light construction Industrial construction Electrical construction Heavy construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management PERT analysis is based on Optimistic time Most likely time All listed here Pessimistic time Optimistic time Most likely time All listed here Pessimistic time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The independent float affects only The particular activity involved Preceding activities None of these Succeeding activities The particular activity involved Preceding activities None of these Succeeding activities ANSWER DOWNLOAD EXAMIANS APP