Construction Planning and Management A construction schedule is prepared after collecting Output of machinery Output of labour Number of operations All listed here Output of machinery Output of labour Number of operations All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the network shown in the given figure, the expected time for the activity All listed here 3-4 is 8 2-3 is 7 1-2 is 4 All listed here 3-4 is 8 2-3 is 7 1-2 is 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Pick up the PERT event from the following: Digging of foundation completed Digging of foundation started Laying of concrete started All listed here Digging of foundation completed Digging of foundation started Laying of concrete started All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the critical path method of construction planning, Free Float can be.1. Greater than Total Float.2. Greater than Independent Float3. Equal to Total Float.4. Less than Independent Float 1 and 4 are correct 1 and 2 are correct 1 and 4 are correct 2 and 3 are correct 1 and 4 are correct 1 and 2 are correct 1 and 4 are correct 2 and 3 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The first method invented for planning projects, was Critical path method (CPM) Programme Evaluation and Review Technique (PERT) Bar chart method Milestone chart Critical path method (CPM) Programme Evaluation and Review Technique (PERT) Bar chart method Milestone chart ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be to + 4tm+ tp/4 to + 3tm+ tp/3 to + 4tm+ tp/5 to + 4tm+ tp/6 to + 4tm+ tp/4 to + 3tm+ tp/3 to + 4tm+ tp/5 to + 4tm+ tp/6 ANSWER DOWNLOAD EXAMIANS APP