Construction Planning and Management A construction schedule is prepared after collecting Output of machinery All listed here Number of operations Output of labour Output of machinery All listed here Number of operations Output of labour ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be Performed at slower rate in 15 days All listed here Started 5 days later Completed 5 days later Performed at slower rate in 15 days All listed here Started 5 days later Completed 5 days later ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good EF = ES + D All listed here LF = LS + D LS = LF - D EF = ES + D All listed here LF = LS + D LS = LF - D ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Rolling resistance of a wheel depends upon(i) Vehicle load(ii) Grade(iii) Ground conditions Only (i) is correct (ii) and (iii) are correct (i) and (ii) are correct (i) and (iii) are correct Only (i) is correct (ii) and (iii) are correct (i) and (ii) are correct (i) and (iii) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While filling the tender for any work, the contractor considers Site survey All listed here Availability of labour Availability of construction materials Site survey All listed here Availability of labour Availability of construction materials ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The salient feature of functional organization is Each individual maintains functional efficiency Separation of planning and design part All listed here Strict adherence to specifications Each individual maintains functional efficiency Separation of planning and design part All listed here Strict adherence to specifications ANSWER DOWNLOAD EXAMIANS APP