Construction Planning and Management A construction schedule is prepared after collecting All listed here Output of machinery Output of labour Number of operations All listed here Output of machinery Output of labour Number of operations ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be Performed at slower rate in 15 days All listed here Started 5 days later Completed 5 days later Performed at slower rate in 15 days All listed here Started 5 days later Completed 5 days later ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is 14 19 None of these 24 14 19 None of these 24 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Residential buildings are treated as Private construction Light construction Heavy construction Industrial construction Private construction Light construction Heavy construction Industrial construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following features/factors: 1. Projects are of the non-repetitive type 2. Time required need not be known 3. Time required is known precisely 4. Events have been established for planning 5. Emphasis is given to activities of project PERT is preferred for planning because of 1, 3 and 4 3, 4 and 5 1, 2 and 5 1, 2 and 4 1, 3 and 4 3, 4 and 5 1, 2 and 5 1, 2 and 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The probability of completion of any activity within its expected time is 0.999 0.841 1 0.5 0.999 0.841 1 0.5 ANSWER DOWNLOAD EXAMIANS APP