Construction Planning and Management A construction schedule is prepared after collecting Output of machinery All listed here Number of operations Output of labour Output of machinery All listed here Number of operations Output of labour ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following earth moving machines has the shortest cycle time? Clam shell Hoe Dipper shovel Drag line Clam shell Hoe Dipper shovel Drag line ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is 15 35 25 20 15 35 25 20 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion (A): Activity 57 is critical.Reason (R): Earliest finish time and latest finish time for events 57 are same Both A and R is correct R is correct but A is not correct A is correct but R is not correct Both A and R is incorrect Both A and R is correct R is correct but A is not correct A is correct but R is not correct Both A and R is incorrect ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following is a weakness of bar chart? Interdependencies of activities Uncertainties Project progress All of these Interdependencies of activities Uncertainties Project progress All of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Railway projects are treated as Heavy construction None of these Light construction Industrial construction Heavy construction None of these Light construction Industrial construction ANSWER DOWNLOAD EXAMIANS APP