Construction Planning and Management A construction schedule is prepared after collecting Output of labour All listed here Number of operations Output of machinery Output of labour All listed here Number of operations Output of machinery ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path May be longest May be shortest Is always shortest Is always longest May be longest May be shortest Is always shortest Is always longest ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The critical activity has Zero float None of these Maximum float Minimum float Zero float None of these Maximum float Minimum float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The Overall in-charge of an organization at the site responsible for the execution of the works, is Executive Engineer Engineer Junior Engineer Assistant Engineer Executive Engineer Engineer Junior Engineer Assistant Engineer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction:1. Concreting of roof slabs2. Brick-jelly lime concrete terracing3. Erection of form work for slab4. Construction of parapet wall in terraceThe correct sequence of these activities is 1, 3, 4, 2 1, 3, 2, 4 3, 1, 2, 4 3, 1, 4, 2 1, 3, 4, 2 1, 3, 2, 4 3, 1, 2, 4 3, 1, 4, 2 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as Free float Total float Interfering float Duration Free float Total float Interfering float Duration ANSWER DOWNLOAD EXAMIANS APP