Construction Planning and Management A construction schedule is prepared after collecting Output of machinery Output of labour All listed here Number of operations Output of machinery Output of labour All listed here Number of operations ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Economic saving of time results by crashing Cheapest critical activity Cheapest noncritical activity Costliest critical activity Costliest noncritical activity Cheapest critical activity Cheapest noncritical activity Costliest critical activity Costliest noncritical activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations: 1. Drilling 2. Blasting 3. Mucking 4. Placing steel 5. Placing concrete The correct sequence of these operations in tunnel construction is 1, 3, 2, 4, 5 1, 3, 4, 2, 5 1, 2, 3, 4, 5 1, 2, 4, 3, 5 1, 3, 2, 4, 5 1, 3, 4, 2, 5 1, 2, 3, 4, 5 1, 2, 4, 3, 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the output of a drag-line for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be Less than X Any of the above More than X Equal to X Less than X Any of the above More than X Equal to X ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Construction team means An owner An engineer All listed here An architect An owner An engineer All listed here An architect ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively 4 and 5/6 3.5 and 25/36 5 and 25/36 3.5 and 5/6 4 and 5/6 3.5 and 25/36 5 and 25/36 3.5 and 5/6 ANSWER DOWNLOAD EXAMIANS APP