Construction Planning and Management A construction schedule is prepared after collecting Output of machinery All listed here Output of labour Number of operations Output of machinery All listed here Output of labour Number of operations ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is 3 4 1 2 3 4 1 2 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion A: For a given depth of cut, the output of a power shovel can be increased by decreasing the angle of swing.Reason R: If the angle of swing is decreased, the cycle time will be decreased. Both A and R is true but R is not the correct explanation of A A is true but R is false Both A and R is true and R is the correct explanation of A A is false but R is true Both A and R is true but R is not the correct explanation of A A is true but R is false Both A and R is true and R is the correct explanation of A A is false but R is true ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The area under the Beta distribution curve is divided into two equal parts by Optimistic time Most likely time Pessimistic time Expected time Optimistic time Most likely time Pessimistic time Expected time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The reduction in project time normally results in Increasing the direct cost and decreasing the indirect cost Increasing the direct cost and indirect cost both Decreasing the direct cost and indirect cost both Decreasing the direct cost and increasing indirect cost Increasing the direct cost and decreasing the indirect cost Increasing the direct cost and indirect cost both Decreasing the direct cost and indirect cost both Decreasing the direct cost and increasing indirect cost ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is 20 25 35 15 20 25 35 15 ANSWER DOWNLOAD EXAMIANS APP