Construction Planning and Management A construction schedule is prepared after collecting Number of operations Output of labour Output of machinery All listed here Number of operations Output of labour Output of machinery All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be Performed at slower rate in 15 days All listed here Completed 5 days later Started 5 days later Performed at slower rate in 15 days All listed here Completed 5 days later Started 5 days later ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion (A): Activity 57 is critical.Reason (R): Earliest finish time and latest finish time for events 57 are same R is correct but A is not correct Both A and R is correct A is correct but R is not correct Both A and R is incorrect R is correct but A is not correct Both A and R is correct A is correct but R is not correct Both A and R is incorrect ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The critical activity has Zero float Maximum float None of these Minimum float Zero float Maximum float None of these Minimum float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For excavating utility trenches with precise control of depth, the excavation equipment used is Shovel Hoe None of these Dragline Shovel Hoe None of these Dragline ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the output of a drag-line for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be Any of the above More than X Less than X Equal to X Any of the above More than X Less than X Equal to X ANSWER DOWNLOAD EXAMIANS APP