Construction Planning and Management A construction schedule is prepared after collecting Output of labour Output of machinery All listed here Number of operations Output of labour Output of machinery All listed here Number of operations ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Float Duration Event Constraint Float Duration Event Constraint ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Earliest finish of an activity is always Less than or equal to earliest event time of the following node Greater than earliest event time of the following node Less than earliest event time of the following node Greater than or equal to earliest event time of the following node Less than or equal to earliest event time of the following node Greater than earliest event time of the following node Less than earliest event time of the following node Greater than or equal to earliest event time of the following node ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management During the construction period, price variation clause in contracts caters to Variation in cost in materials element, labour element and petrol-oil-lubricant element Increase in rates of only important materials Rate of inflation Variation in total cost of the project on an ad hoc basis Variation in cost in materials element, labour element and petrol-oil-lubricant element Increase in rates of only important materials Rate of inflation Variation in total cost of the project on an ad hoc basis ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In PERT analysis, the time estimates of activities and probability of their occurrence follow Beta distribution curve None of these Normal distribution curve Poisson's distribution curve Beta distribution curve None of these Normal distribution curve Poisson's distribution curve ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion (A): Activity 57 is critical.Reason (R): Earliest finish time and latest finish time for events 57 are same A is correct but R is not correct Both A and R is correct Both A and R is incorrect R is correct but A is not correct A is correct but R is not correct Both A and R is correct Both A and R is incorrect R is correct but A is not correct ANSWER DOWNLOAD EXAMIANS APP