Construction Planning and Management A construction schedule is prepared after collecting Output of machinery All listed here Number of operations Output of labour Output of machinery All listed here Number of operations Output of labour ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations:1. Drilling2. Blasting3. Mucking4. Placing steel5. Placing concreteThe correct sequence of these operations in tunnel construction is 1, 3, 4, 2, 5 1, 3, 2, 4, 5 1, 2, 3, 4, 5 1, 2, 4, 3, 5 1, 3, 4, 2, 5 1, 3, 2, 4, 5 1, 2, 3, 4, 5 1, 2, 4, 3, 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The basic action involved in sheep foot rolling is Kneading Vibration Pressing Tamping Kneading Vibration Pressing Tamping ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Whenever an activity has zero total float, then Free float and independent float both must be zero Free float of the activity must be zero but independent float need not be zero Free float and independent float both need not be zero Independent float must be zero but free float need not be zero Free float and independent float both must be zero Free float of the activity must be zero but independent float need not be zero Free float and independent float both need not be zero Independent float must be zero but free float need not be zero ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively 4 and 5/6 5 and 25/36 3.5 and 5/6 3.5 and 25/36 4 and 5/6 5 and 25/36 3.5 and 5/6 3.5 and 25/36 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawler-mounted and pneumatic tyre-mounted machines would be respectively 75 and 83 80 and 90 85 and 75 90 and 80 75 and 83 80 and 90 85 and 75 90 and 80 ANSWER DOWNLOAD EXAMIANS APP