Construction Planning and Management A construction schedule is prepared after collecting All listed here Number of operations Output of machinery Output of labour All listed here Number of operations Output of machinery Output of labour ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction:1. Concreting of roof slabs2. Brick-jelly lime concrete terracing3. Erection of form work for slab4. Construction of parapet wall in terraceThe correct sequence of these activities is 3, 1, 2, 4 3, 1, 4, 2 1, 3, 4, 2 1, 3, 2, 4 3, 1, 2, 4 3, 1, 4, 2 1, 3, 4, 2 1, 3, 2, 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is 14 19 24 None of these 14 19 24 None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given size of bucket, the ideal output of a dragline will be least in Sand and gravel Good common earth Wet sticky clay Moist loam Sand and gravel Good common earth Wet sticky clay Moist loam ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The maximum rimpull in the first gear of a tractor while towing a load is 6300 kg. The tractor weighs 12.5 tonnes and is operating along a 2 percent upgrade and the rolling resistance is 45 kg/tonne. Pull available for towing the load is 2975 kg 5515 kg 3425 kg 4350 kg 2975 kg 5515 kg 3425 kg 4350 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The area under the Beta distribution curve is divided into two equal parts by Expected time Pessimistic time Optimistic time Most likely time Expected time Pessimistic time Optimistic time Most likely time ANSWER DOWNLOAD EXAMIANS APP