Construction Planning and Management If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be 15.9% and 97.7% 97.7 % and 15.9% 97.7% and 84.1% 2.3% and 84.1% 15.9% and 97.7% 97.7 % and 15.9% 97.7% and 84.1% 2.3% and 84.1% ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Wheeled tractors are replacing crawler tractors because 1. Wheeled tractors travel faster. 2. Crawler tractors are more expensive. 3. Track parts of a crawler wear out quickly. 4. Crawler tractors have stick control. of following statements 1, 2 and 3 are correct 1, 2 and 4 are correct 2, 3 and 4 are correct 1, 3 and 4 are correct 1, 2 and 3 are correct 1, 2 and 4 are correct 2, 3 and 4 are correct 1, 3 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A construction schedule is prepared after collecting All listed here Output of labour Output of machinery Number of operations All listed here Output of labour Output of machinery Number of operations ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The probability of completion of any activity within its expected time is 1 0.999 0.841 0.5 1 0.999 0.841 0.5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Interfering float is the difference between Total float and independent float Free float and independent float Total float and free float None of these Total float and independent float Free float and independent float Total float and free float None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Pick up the PERT event from the following: Digging of foundation completed All listed here Digging of foundation started Laying of concrete started Digging of foundation completed All listed here Digging of foundation started Laying of concrete started ANSWER DOWNLOAD EXAMIANS APP