Construction Planning and Management
If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be

97.7 % and 15.9%
2.3% and 84.1%
15.9% and 97.7%
97.7% and 84.1%

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Free float is mainly used to

Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities
Identify the activities, which can be delayed without affecting the total float of succeeding activity
Identify the activities which can be delayed without affecting the total float of preceding activity
Establish priorities

ANSWER DOWNLOAD EXAMIANS APP