Construction Planning and Management The probability of completion of any activity within its expected time is 1 0.5 0.841 0.999 1 0.5 0.841 0.999 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For which of the following materials, the output of power shovels for a fixed shovel size will be maximum Well blasted rock Good common earth Moist loam Wet sticky clay Well blasted rock Good common earth Moist loam Wet sticky clay ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management PERT technique of network analysis is mainly useful for Small projects Deterministic activities Research and development projects Large and complex projects Small projects Deterministic activities Research and development projects Large and complex projects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following is not a PERT event? Class is being attended Sessional work completed Bus starts from Jaipur Site investigation started Class is being attended Sessional work completed Bus starts from Jaipur Site investigation started ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The constraints in case of resource smoothening operation would be Resources Both resources and project duration time None of these Project duration time Resources Both resources and project duration time None of these Project duration time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations: 1. Drilling 2. Blasting 3. Mucking 4. Placing steel 5. Placing concrete The correct sequence of these operations in tunnel construction is 1, 2, 4, 3, 5 1, 3, 4, 2, 5 1, 2, 3, 4, 5 1, 3, 2, 4, 5 1, 2, 4, 3, 5 1, 3, 4, 2, 5 1, 2, 3, 4, 5 1, 3, 2, 4, 5 ANSWER DOWNLOAD EXAMIANS APP