Construction Planning and Management The probability of completion of any activity within its expected time is 0.999 0.5 1 0.841 0.999 0.5 1 0.841 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The reduction in project time normally results in Decreasing the direct cost and increasing indirect cost Increasing the direct cost and decreasing the indirect cost Increasing the direct cost and indirect cost both Decreasing the direct cost and indirect cost both Decreasing the direct cost and increasing indirect cost Increasing the direct cost and decreasing the indirect cost Increasing the direct cost and indirect cost both Decreasing the direct cost and indirect cost both ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the network shown in the given figure, the expected time for the activity 1-2 is 4 3-4 is 8 All listed here 2-3 is 7 1-2 is 4 3-4 is 8 All listed here 2-3 is 7 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The constraints in case of resource smoothening operation would be Both resources and project duration time None of these Resources Project duration time Both resources and project duration time None of these Resources Project duration time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management An earth moving equipment costs Rs. 5,00,000 and has an estimated life of 10 years and a salvage value of Rs. 50,000. What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069? Rs. 37950 Rs. 31050 Rs. 34500 Rs. 50000 Rs. 37950 Rs. 31050 Rs. 34500 Rs. 50000 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management What estimate would you give for the variance in above problem ? 54 81 36 9 54 81 36 9 ANSWER DOWNLOAD EXAMIANS APP