Construction Planning and Management During the construction period, price variation clause in contracts caters to Rate of inflation Increase in rates of only important materials Variation in total cost of the project on an ad hoc basis Variation in cost in materials element, labour element and petrol-oil-lubricant element Rate of inflation Increase in rates of only important materials Variation in total cost of the project on an ad hoc basis Variation in cost in materials element, labour element and petrol-oil-lubricant element ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 2000 cum 500 cum 1500 cum 1000 cum 2000 cum 500 cum 1500 cum 1000 cum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While filling the tender for any work, the contractor considers All listed here Availability of labour Availability of construction materials Site survey All listed here Availability of labour Availability of construction materials Site survey ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawler-mounted and pneumatic tyre-mounted machines would be respectively 75 and 83 90 and 80 85 and 75 80 and 90 75 and 83 90 and 80 85 and 75 80 and 90 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is 4 2 3 1 4 2 3 1 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be All listed here Started 5 days later Completed 5 days later Performed at slower rate in 15 days All listed here Started 5 days later Completed 5 days later Performed at slower rate in 15 days ANSWER DOWNLOAD EXAMIANS APP