Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be Completed 5 days later All listed here Performed at slower rate in 15 days Started 5 days later Completed 5 days later All listed here Performed at slower rate in 15 days Started 5 days later ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawler-mounted and pneumatic tyre-mounted machines would be respectively 75 and 83 80 and 90 90 and 80 85 and 75 75 and 83 80 and 90 90 and 80 85 and 75 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The direct cost of a project with respect to normal time is Infinite Maximum Zero Minimum Infinite Maximum Zero Minimum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Time and progress chart of a construction, is also known as Bar chart Modified Mile stone chart All listed here Gantt chart Bar chart Modified Mile stone chart All listed here Gantt chart ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Railway projects are treated as Industrial construction Heavy construction None of these Light construction Industrial construction Heavy construction None of these Light construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively 5 and 25/36 3.5 and 25/36 4 and 5/6 3.5 and 5/6 5 and 25/36 3.5 and 25/36 4 and 5/6 3.5 and 5/6 ANSWER DOWNLOAD EXAMIANS APP