Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be Performed at slower rate in 15 days Started 5 days later All listed here Completed 5 days later Performed at slower rate in 15 days Started 5 days later All listed here Completed 5 days later ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Power stations are generally treated as Industrial construction Electrical construction Light construction Heavy construction Industrial construction Electrical construction Light construction Heavy construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Residential buildings are treated as Industrial construction Heavy construction Light construction Private construction Industrial construction Heavy construction Light construction Private construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements: In the bar chart planning 1. Interdependence of the operations cannot be portrayed. 2. Progress of work can be measured. 3. Spare time of the activities can be determined. 4. Schedule cannot be updated. 1, 2 and 4 are correct 1, 2 and 3 are correct 1 and 4 are correct 2, 3 and 4 are correct 1, 2 and 4 are correct 1, 2 and 3 are correct 1 and 4 are correct 2, 3 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In the given figure, the network of a project represents None of these Activity of excavation which takes 8 units of time Activity of an excavation of a footing Activity of an excavation which starts at event No. 1 and ends at even No. 2 None of these Activity of excavation which takes 8 units of time Activity of an excavation of a footing Activity of an excavation which starts at event No. 1 and ends at even No. 2 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 2000 cum 1000 cum 500 cum 1500 cum 2000 cum 1000 cum 500 cum 1500 cum ANSWER DOWNLOAD EXAMIANS APP