Construction Planning and Management
If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be

All listed here
Started 5 days later
Performed at slower rate in 15 days
Completed 5 days later

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
In India, are prefabricated components costlier than those of traditional cast-in-situ items that the prefabricated components replace?

No, because of savings in site labour
Yes, because of the very high order of quality control for the factory made components
Yes, because of heavier overheads and handling cost
No, because of repetitive manufacture of a number of elements

ANSWER DOWNLOAD EXAMIANS APP