Construction Planning and Management While filling the tender for any work, the contractor considers All listed here Availability of labour Availability of construction materials Site survey All listed here Availability of labour Availability of construction materials Site survey ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In resources levelling Total duration of project is reduced Cost of project is controlled Total duration of project is increased Uniform demand of resources is achieved Total duration of project is reduced Cost of project is controlled Total duration of project is increased Uniform demand of resources is achieved ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A machine costs Rs. 20000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be Rs. 5220 Rs. 3480 Rs. 6960 Rs. 1740 Rs. 5220 Rs. 3480 Rs. 6960 Rs. 1740 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The salient feature of functional organization is Strict adherence to specifications Separation of planning and design part Each individual maintains functional efficiency All listed here Strict adherence to specifications Separation of planning and design part Each individual maintains functional efficiency All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The grade resistance factor for an earth moving machine can be obtained by multiplying grade percentage by a factor approximately equal to 2 kg/tonne 6 kg/tonne 20 kg/tonne 9 kg/tonne 2 kg/tonne 6 kg/tonne 20 kg/tonne 9 kg/tonne ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as Event Free float Constraint Dummy Event Free float Constraint Dummy ANSWER DOWNLOAD EXAMIANS APP