Construction Planning and Management
If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is

1500 cum
500 cum
2000 cum
1000 cum

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Earliest finish of an activity is always

Less than earliest event time of the following node
Greater than earliest event time of the following node
Greater than or equal to earliest event time of the following node
Less than or equal to earliest event time of the following node

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
During the construction period, price variation clause in contracts caters to

Variation in total cost of the project on an ad hoc basis
Increase in rates of only important materials
Rate of inflation
Variation in cost in materials element, labour element and petrol-oil-lubricant element

ANSWER DOWNLOAD EXAMIANS APP