Construction Planning and Management
If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is

1500 cum
500 cum
2000 cum
1000 cum

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Assertion A: For a given depth of cut, the output of a power shovel can be increased by decreasing the angle of swing.Reason R: If the angle of swing is decreased, the cycle time will be decreased.

A is true but R is false
Both A and R is true and R is the correct explanation of A
A is false but R is true
Both A and R is true but R is not the correct explanation of A

ANSWER DOWNLOAD EXAMIANS APP