Construction Planning and Management The technique for establishing and maintaining priorities among the various jobs of a project, is known Short interval scheduling Critical ratio scheduling Slotting technique for scheduling Event flow scheduling technique Short interval scheduling Critical ratio scheduling Slotting technique for scheduling Event flow scheduling technique ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following is not a PERT event? Class is being attended Site investigation started Sessional work completed Bus starts from Jaipur Class is being attended Site investigation started Sessional work completed Bus starts from Jaipur ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Event Float Duration Constraint Event Float Duration Constraint ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In the given figure, the network of a project represents None of these Activity of an excavation of a footing Activity of excavation which takes 8 units of time Activity of an excavation which starts at event No. 1 and ends at even No. 2 None of these Activity of an excavation of a footing Activity of excavation which takes 8 units of time Activity of an excavation which starts at event No. 1 and ends at even No. 2 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In India, are prefabricated components costlier than those of traditional cast-in-situ items that the prefabricated components replace? No, because of repetitive manufacture of a number of elements No, because of savings in site labour Yes, because of heavier overheads and handling cost Yes, because of the very high order of quality control for the factory made components No, because of repetitive manufacture of a number of elements No, because of savings in site labour Yes, because of heavier overheads and handling cost Yes, because of the very high order of quality control for the factory made components ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction:1. Concreting of roof slabs2. Brick-jelly lime concrete terracing3. Erection of form work for slab4. Construction of parapet wall in terraceThe correct sequence of these activities is 1, 3, 2, 4 1, 3, 4, 2 3, 1, 4, 2 3, 1, 2, 4 1, 3, 2, 4 1, 3, 4, 2 3, 1, 4, 2 3, 1, 2, 4 ANSWER DOWNLOAD EXAMIANS APP