Construction Planning and Management If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be to + 4tm+ tp/4 to + 4tm+ tp/5 to + 4tm+ tp/6 to + 3tm+ tp/3 to + 4tm+ tp/4 to + 4tm+ tp/5 to + 4tm+ tp/6 to + 3tm+ tp/3 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is 19 None of these 14 24 19 None of these 14 24 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having Shortest duration Least cost slope Highest cost slope Longest duration Shortest duration Least cost slope Highest cost slope Longest duration ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management At a work site, statistical quality control of concrete means Reduction in wastage of inspection costs Measurement of risks to eliminate failures Reduction in costs for the removal of defects Applying the theory' of probability to sample testing or inspection Reduction in wastage of inspection costs Measurement of risks to eliminate failures Reduction in costs for the removal of defects Applying the theory' of probability to sample testing or inspection ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The first method invented for planning projects, was Critical path method (CPM) Milestone chart Bar chart method Programme Evaluation and Review Technique (PERT) Critical path method (CPM) Milestone chart Bar chart method Programme Evaluation and Review Technique (PERT) ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The basic action involved in sheep foot rolling is Pressing Kneading Tamping Vibration Pressing Kneading Tamping Vibration ANSWER DOWNLOAD EXAMIANS APP