Construction Planning and Management If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good All listed here LS = LF - D LF = LS + D EF = ES + D All listed here LS = LF - D LF = LS + D EF = ES + D ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the network shown in the given figure, the expected time for the activity All listed here 2-3 is 7 1-2 is 4 3-4 is 8 All listed here 2-3 is 7 1-2 is 4 3-4 is 8 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path May be shortest May be longest Is always shortest Is always longest May be shortest May be longest Is always shortest Is always longest ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Residential buildings are treated as Private construction Heavy construction Light construction Industrial construction Private construction Heavy construction Light construction Industrial construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 9 days 15 days 8 days 10 days 9 days 15 days 8 days 10 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The direct cost of a project with respect to normal time is Infinite Minimum Maximum Zero Infinite Minimum Maximum Zero ANSWER DOWNLOAD EXAMIANS APP