Construction Planning and Management If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good All listed here EF = ES + D LF = LS + D LS = LF - D All listed here EF = ES + D LF = LS + D LS = LF - D ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Completion of an activity on CPM network diagram, is generally known Node Event Connector All listed here Node Event Connector All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The grade resistance factor for an earth moving machine can be obtained by multiplying grade percentage by a factor approximately equal to 2 kg/tonne 9 kg/tonne 20 kg/tonne 6 kg/tonne 2 kg/tonne 9 kg/tonne 20 kg/tonne 6 kg/tonne ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the gross vehicle weight of a truck is 30 tonne and rolling resistance is 30 kg/tonne, then the tractive effort required to keep the truck moving at a uniform speed is 300 kg 900 kg 1000 kg 30 kg 300 kg 900 kg 1000 kg 30 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Economic saving of time results by crashing Costliest critical activity Costliest noncritical activity Cheapest critical activity Cheapest noncritical activity Costliest critical activity Costliest noncritical activity Cheapest critical activity Cheapest noncritical activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Total float for any activity is defined as the difference between Its earliest finish time and earliest start time for its successor activity Its latest start time and earliest finish time Its latest finish time and earliest start time for its successor activity Its latest start time and earliest start time Its earliest finish time and earliest start time for its successor activity Its latest start time and earliest finish time Its latest finish time and earliest start time for its successor activity Its latest start time and earliest start time ANSWER DOWNLOAD EXAMIANS APP