Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 8 days 9 days 10 days 15 days 8 days 9 days 10 days 15 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The most suitable type of equipment for compaction of cohesive soils is Tampers Vibratory rollers Sheep foot rollers Smooth-wheeled rollers Tampers Vibratory rollers Sheep foot rollers Smooth-wheeled rollers ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Interfering float is the difference between Free float and independent float Total float and free float Total float and independent float None of these Free float and independent float Total float and free float Total float and independent float None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management CPM is All listed here Is based on time estimate Synthesising in concepts Is built of activities oriented programme All listed here Is based on time estimate Synthesising in concepts Is built of activities oriented programme ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Wheeled tractors are replacing crawler tractors because1. Wheeled tractors travel faster.2. Crawler tractors are more expensive.3. Track parts of a crawler wear out quickly.4. Crawler tractors have stick control.of following statements 2, 3 and 4 are correct 1, 2 and 4 are correct 1, 3 and 4 are correct 1, 2 and 3 are correct 2, 3 and 4 are correct 1, 2 and 4 are correct 1, 3 and 4 are correct 1, 2 and 3 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Economic saving of time results by crashing Cheapest critical activity Costliest noncritical activity Costliest critical activity Cheapest noncritical activity Cheapest critical activity Costliest noncritical activity Costliest critical activity Cheapest noncritical activity ANSWER DOWNLOAD EXAMIANS APP