Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 8 days 9 days 15 days 10 days 8 days 9 days 15 days 10 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements: In the bar chart planning 1. Interdependence of the operations cannot be portrayed. 2. Progress of work can be measured. 3. Spare time of the activities can be determined. 4. Schedule cannot be updated. 1, 2 and 3 are correct 1, 2 and 4 are correct 1 and 4 are correct 2, 3 and 4 are correct 1, 2 and 3 are correct 1, 2 and 4 are correct 1 and 4 are correct 2, 3 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In resources levelling Total duration of project is reduced Total duration of project is increased Uniform demand of resources is achieved Cost of project is controlled Total duration of project is reduced Total duration of project is increased Uniform demand of resources is achieved Cost of project is controlled ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management CPM is All listed here Is built of activities oriented programme Synthesising in concepts Is based on time estimate All listed here Is built of activities oriented programme Synthesising in concepts Is based on time estimate ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Railway projects are treated as None of these Heavy construction Light construction Industrial construction None of these Heavy construction Light construction Industrial construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements: In the critical path method of construction planning, Free Float can be. 1. Greater than Total Float. 2. Greater than Independent Float 3. Equal to Total Float. 4. Less than Independent Float 1 and 4 are correct 1 and 2 are correct 2 and 3 are correct 1 and 4 are correct 1 and 4 are correct 1 and 2 are correct 2 and 3 are correct 1 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP