Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 8 days 15 days 9 days 10 days 8 days 15 days 9 days 10 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Updating may result in All of these Change of critical path Increase of project completion time Decrease of project completion time All of these Change of critical path Increase of project completion time Decrease of project completion time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be Started 5 days later Completed 5 days later Performed at slower rate in 15 days All listed here Started 5 days later Completed 5 days later Performed at slower rate in 15 days All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the network shown in the given figure, the expected time for the activity 2-3 is 7 All listed here 1-2 is 4 3-4 is 8 2-3 is 7 All listed here 1-2 is 4 3-4 is 8 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Latest start of an activity is always greater than or equal to latest event time of preceding node less than latest event time of preceding node less than or equal to latest event time of preceding node equal to latest event time of preceding node greater than or equal to latest event time of preceding node less than latest event time of preceding node less than or equal to latest event time of preceding node equal to latest event time of preceding node ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The independent float affects only Preceding activities The particular activity involved Succeeding activities None of these Preceding activities The particular activity involved Succeeding activities None of these ANSWER DOWNLOAD EXAMIANS APP