Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 15 days 8 days 10 days 9 days 15 days 8 days 10 days 9 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In PERT analysis, the time estimates of activities and probability of their occurrence follow None of these Poisson's distribution curve Normal distribution curve Beta distribution curve None of these Poisson's distribution curve Normal distribution curve Beta distribution curve ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management An earth moving equipment costs Rs. 5,00,000 and has an estimated life of 10 years and a salvage value of Rs. 50,000. What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069? Rs. 31050 Rs. 34500 Rs. 50000 Rs. 37950 Rs. 31050 Rs. 34500 Rs. 50000 Rs. 37950 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management An excavator costs Rs. 20,00,000 and has an estimated life of 8 years. It has no salvage value at the end of 8 years. The book value of the excavator at the end of 3 years using general double declining balance method is Rs. 8,75,000 Rs. 8,43,750 Rs. 10,50,000 Rs. 11,56,250 Rs. 8,75,000 Rs. 8,43,750 Rs. 10,50,000 Rs. 11,56,250 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as Event Constraint Free float Dummy Event Constraint Free float Dummy ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The most suitable type of equipment for compaction of cohesive soils is Tampers Vibratory rollers Smooth-wheeled rollers Sheep foot rollers Tampers Vibratory rollers Smooth-wheeled rollers Sheep foot rollers ANSWER DOWNLOAD EXAMIANS APP