Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 9 days 15 days 10 days 8 days 9 days 15 days 10 days 8 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the execution of a project, a contractor is A person An agency All listed here A firm A person An agency All listed here A firm ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following represents an event? Concrete cured Selecting sites Plastering of walls Fixing of door Concrete cured Selecting sites Plastering of walls Fixing of door ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements: In the critical path method of construction planning, Free Float can be. 1. Greater than Total Float. 2. Greater than Independent Float 3. Equal to Total Float. 4. Less than Independent Float 2 and 3 are correct 1 and 4 are correct 1 and 2 are correct 1 and 4 are correct 2 and 3 are correct 1 and 4 are correct 1 and 2 are correct 1 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Preliminary project report for a road project must contain The detailed estimated cost based on detailed design The soil survey, traffic survey, concept design and approximate cost The several alternatives of the project that have been considered The contract documents for inviting tenders The detailed estimated cost based on detailed design The soil survey, traffic survey, concept design and approximate cost The several alternatives of the project that have been considered The contract documents for inviting tenders ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Latest start of an activity is always greater than or equal to latest event time of preceding node less than or equal to latest event time of preceding node less than latest event time of preceding node equal to latest event time of preceding node greater than or equal to latest event time of preceding node less than or equal to latest event time of preceding node less than latest event time of preceding node equal to latest event time of preceding node ANSWER DOWNLOAD EXAMIANS APP