Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 10 days 8 days 9 days 15 days 10 days 8 days 9 days 15 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Total float for any activity is defined as the difference between Its latest start time and earliest start time Its latest start time and earliest finish time Its latest finish time and earliest start time for its successor activity Its earliest finish time and earliest start time for its successor activity Its latest start time and earliest start time Its latest start time and earliest finish time Its latest finish time and earliest start time for its successor activity Its earliest finish time and earliest start time for its successor activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The salient feature of functional organization is Separation of planning and design part Each individual maintains functional efficiency All listed here Strict adherence to specifications Separation of planning and design part Each individual maintains functional efficiency All listed here Strict adherence to specifications ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Power stations are generally treated as Heavy construction Electrical construction Industrial construction Light construction Heavy construction Electrical construction Industrial construction Light construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management At a work site, statistical quality control of concrete means Reduction in wastage of inspection costs Reduction in costs for the removal of defects Measurement of risks to eliminate failures Applying the theory' of probability to sample testing or inspection Reduction in wastage of inspection costs Reduction in costs for the removal of defects Measurement of risks to eliminate failures Applying the theory' of probability to sample testing or inspection ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good LS = LF - D All listed here EF = ES + D LF = LS + D LS = LF - D All listed here EF = ES + D LF = LS + D ANSWER DOWNLOAD EXAMIANS APP