Construction Planning and Management Free float for any activity is defined as the difference between its earliest finish time and latest start time for its successor activity its latest start time and earliest start time its earliest finish time and earliest start time for its successor activity its latest finish time and earliest start time for its successor activity its earliest finish time and latest start time for its successor activity its latest start time and earliest start time its earliest finish time and earliest start time for its successor activity its latest finish time and earliest start time for its successor activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations: 1. Drilling 2. Blasting 3. Mucking 4. Placing steel 5. Placing concrete The correct sequence of these operations in tunnel construction is 1, 3, 4, 2, 5 1, 2, 4, 3, 5 1, 2, 3, 4, 5 1, 3, 2, 4, 5 1, 3, 4, 2, 5 1, 2, 4, 3, 5 1, 2, 3, 4, 5 1, 3, 2, 4, 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management PERT analysis is based on Most likely time All listed here Pessimistic time Optimistic time Most likely time All listed here Pessimistic time Optimistic time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Total float for any activity is defined as the difference between Its latest finish time and earliest start time for its successor activity Its latest start time and earliest finish time Its earliest finish time and earliest start time for its successor activity Its latest start time and earliest start time Its latest finish time and earliest start time for its successor activity Its latest start time and earliest finish time Its earliest finish time and earliest start time for its successor activity Its latest start time and earliest start time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management CPM is All listed here Synthesising in concepts Is based on time estimate Is built of activities oriented programme All listed here Synthesising in concepts Is based on time estimate Is built of activities oriented programme ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path method Is an improvement upon bar chart method Provides a realistic approach to daily problems Avoids delays which are very common in bar charts All listed here Is an improvement upon bar chart method Provides a realistic approach to daily problems Avoids delays which are very common in bar charts All listed here ANSWER DOWNLOAD EXAMIANS APP