Construction Planning and Management Free float for any activity is defined as the difference between its latest finish time and earliest start time for its successor activity its latest start time and earliest start time its earliest finish time and earliest start time for its successor activity its earliest finish time and latest start time for its successor activity its latest finish time and earliest start time for its successor activity its latest start time and earliest start time its earliest finish time and earliest start time for its successor activity its earliest finish time and latest start time for its successor activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management At a work site, statistical quality control of concrete means Reduction in costs for the removal of defects Reduction in wastage of inspection costs Applying the theory' of probability to sample testing or inspection Measurement of risks to eliminate failures Reduction in costs for the removal of defects Reduction in wastage of inspection costs Applying the theory' of probability to sample testing or inspection Measurement of risks to eliminate failures ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A wheeled tractor hauling unit is working on firm earth. The total loaded weight distribution of this unit is:Drive wheels: 25000 kgScraper wheels: 10000 kgIf the coefficient of traction for wheeled tractor on firm earth is 0.5, the rimpull which this tractor can exert without slipping is 10000 kg 5000 kg 12500 kg 22500 kg 10000 kg 5000 kg 12500 kg 22500 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Total float for any activity is defined as the difference between Its latest finish time and earliest start time for its successor activity Its latest start time and earliest finish time Its earliest finish time and earliest start time for its successor activity Its latest start time and earliest start time Its latest finish time and earliest start time for its successor activity Its latest start time and earliest finish time Its earliest finish time and earliest start time for its successor activity Its latest start time and earliest start time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following is a weakness of bar chart? Project progress Interdependencies of activities All of these Uncertainties Project progress Interdependencies of activities All of these Uncertainties ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The direct cost of a project with respect to normal time is Maximum Zero Infinite Minimum Maximum Zero Infinite Minimum ANSWER DOWNLOAD EXAMIANS APP