Construction Planning and Management
The object of technical planning, is

Preparation of specifications
Initiating the procurement action of resources
All listed here
Preparation of estimates

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then

expected time of activity B is greater than the expected time of activity A
expected time of both activities A and B are same
None of these
expected time of activity A is greater than the expected time of activity B

ANSWER DOWNLOAD EXAMIANS APP