Construction Planning and Management Batching refers to Weighing accurately, the quantity of each material for a job before mixing Adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch Controlling the total quantity at each batch Controlling the quantity of each material into each batch Weighing accurately, the quantity of each material for a job before mixing Adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch Controlling the total quantity at each batch Controlling the quantity of each material into each batch ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Updating may result in Change of critical path All of these Increase of project completion time Decrease of project completion time Change of critical path All of these Increase of project completion time Decrease of project completion time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The critical activity has Maximum float Zero float Minimum float None of these Maximum float Zero float Minimum float None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Military organization is known as Line organization Line and staff organization Functional organization None of these Line organization Line and staff organization Functional organization None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In India, are prefabricated components costlier than those of traditional cast-in-situ items that the prefabricated components replace? Yes, because of heavier overheads and handling cost Yes, because of the very high order of quality control for the factory made components No, because of savings in site labour No, because of repetitive manufacture of a number of elements Yes, because of heavier overheads and handling cost Yes, because of the very high order of quality control for the factory made components No, because of savings in site labour No, because of repetitive manufacture of a number of elements ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Free float is mainly used to Identify the activities, which can be delayed without affecting the total float of succeeding activity Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities Identify the activities which can be delayed without affecting the total float of preceding activity Establish priorities Identify the activities, which can be delayed without affecting the total float of succeeding activity Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities Identify the activities which can be delayed without affecting the total float of preceding activity Establish priorities ANSWER DOWNLOAD EXAMIANS APP