Construction Planning and Management For a given size of bucket, the ideal output of a dragline will be least in Wet sticky clay Sand and gravel Good common earth Moist loam Wet sticky clay Sand and gravel Good common earth Moist loam ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A tractor whose weight is 20 tonnes has a drawbar pull of 2500 kg, when operated on a level road having a rolling resistance of 30 kg per tonne. If this tractor is operated on a level road having a rolling resistance of 40 kg per tonne, then the drawbar pull of the tractor will Increase by 250 kg Increase by 200 kg Reduce by 200 kg Reduce by 250 kg Increase by 250 kg Increase by 200 kg Reduce by 200 kg Reduce by 250 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Pick up the correct statement from the following with regards to C.P.M. network analysis of projects Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time All listed here Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the bar chart planning1. Interdependence of the operations cannot be portrayed.2. Progress of work can be measured.3. Spare time of the activities can be determined.4. Schedule cannot be updated. 1 and 4 are correct 2, 3 and 4 are correct 1, 2 and 3 are correct 1, 2 and 4 are correct 1 and 4 are correct 2, 3 and 4 are correct 1, 2 and 3 are correct 1, 2 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Earliest finish of an activity is always Less than or equal to earliest event time of the following node Greater than earliest event time of the following node Greater than or equal to earliest event time of the following node Less than earliest event time of the following node Less than or equal to earliest event time of the following node Greater than earliest event time of the following node Greater than or equal to earliest event time of the following node Less than earliest event time of the following node ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion (A): Activity 57 is critical.Reason (R): Earliest finish time and latest finish time for events 57 are same Both A and R is incorrect Both A and R is correct A is correct but R is not correct R is correct but A is not correct Both A and R is incorrect Both A and R is correct A is correct but R is not correct R is correct but A is not correct ANSWER DOWNLOAD EXAMIANS APP