Construction Planning and Management Slack time refers to An event None of these An activity Both event and activity An event None of these An activity Both event and activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A machine costs Rs. 20000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be Rs. 1740 Rs. 3480 Rs. 6960 Rs. 5220 Rs. 1740 Rs. 3480 Rs. 6960 Rs. 5220 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be to + 4tm+ tp/6 to + 4tm+ tp/4 to + 3tm+ tp/3 to + 4tm+ tp/5 to + 4tm+ tp/6 to + 4tm+ tp/4 to + 3tm+ tp/3 to + 4tm+ tp/5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management What estimate would you give for the variance in above problem ? 36 9 54 81 36 9 54 81 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A father notes that when his teenage daughter uses the telephone, she takes not less than 6 minutes for a call and som? times as much as an hour. Fifteen minutes call are more frequent than calls of any other duration. If these phone calls were an activity in PERT project, then phone calls expected duration will be 21 minutes 15 minutes 20.143 minutes 27 minutes 21 minutes 15 minutes 20.143 minutes 27 minutes ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following earth moving machines has the shortest cycle time? Clam shell Dipper shovel Drag line Hoe Clam shell Dipper shovel Drag line Hoe ANSWER DOWNLOAD EXAMIANS APP