Construction Planning and Management Military organization is known as Functional organization None of these Line organization Line and staff organization Functional organization None of these Line organization Line and staff organization ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following features/factors:1. Projects are of the non-repetitive type2. Time required need not be known3. Time required is known precisely4. Events have been established for planning5. Emphasis is given to activities of projectPERT is preferred for planning because of 1, 2 and 5 1, 3 and 4 3, 4 and 5 1, 2 and 4 1, 2 and 5 1, 3 and 4 3, 4 and 5 1, 2 and 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Railway projects are treated as Heavy construction None of these Industrial construction Light construction Heavy construction None of these Industrial construction Light construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is None of these 14 19 24 None of these 14 19 24 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following features/factors: 1. Projects are of the non-repetitive type 2. Time required need not be known 3. Time required is known precisely 4. Events have been established for planning 5. Emphasis is given to activities of project PERT is preferred for planning because of 1, 2 and 4 1, 2 and 5 1, 3 and 4 3, 4 and 5 1, 2 and 4 1, 2 and 5 1, 3 and 4 3, 4 and 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time which results in the least possible construction cost of an activity, is known as Crash time Normal time Slow time Standard time Crash time Normal time Slow time Standard time ANSWER DOWNLOAD EXAMIANS APP