Construction Planning and Management The time which results in the least possible construction cost of an activity, is known as Crash time Slow time Normal time Standard time Crash time Slow time Normal time Standard time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management During the construction period, price variation clause in contracts caters to Variation in total cost of the project on an ad hoc basis Rate of inflation Variation in cost in materials element, labour element and petrol-oil-lubricant element Increase in rates of only important materials Variation in total cost of the project on an ad hoc basis Rate of inflation Variation in cost in materials element, labour element and petrol-oil-lubricant element Increase in rates of only important materials ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A critical ratio scheduling None of these Is a dynamic system Determines the status of each activity Adjusts automatically changes in activity progress None of these Is a dynamic system Determines the status of each activity Adjusts automatically changes in activity progress ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion A: For a given depth of cut, the output of a power shovel can be increased by decreasing the angle of swing.Reason R: If the angle of swing is decreased, the cycle time will be decreased. Both A and R is true and R is the correct explanation of A A is false but R is true A is true but R is false Both A and R is true but R is not the correct explanation of A Both A and R is true and R is the correct explanation of A A is false but R is true A is true but R is false Both A and R is true but R is not the correct explanation of A ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The main principle of an organization, is Unity of command Effective control at all levels Delegation of authority All listed here Unity of command Effective control at all levels Delegation of authority All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Crash project duration is obtained by summing the Normal durations for all the activities Crash durations for all activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Normal durations for all the activities Crash durations for all activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities ANSWER DOWNLOAD EXAMIANS APP