Construction Planning and Management The time which results in the least possible construction cost of an activity, is known as Standard time Normal time Crash time Slow time Standard time Normal time Crash time Slow time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following surfaces will give highest rolling resistance for a rubber tyred vehicle? Concrete Asphalt Firm earth Loose sand Concrete Asphalt Firm earth Loose sand ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the output of a drag-line for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be More than X Equal to X Any of the above Less than X More than X Equal to X Any of the above Less than X ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time corresponding to minimum total project cost is Between normal time and crash time Normal time Optimistic time Crash time Between normal time and crash time Normal time Optimistic time Crash time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The normal time required for the completion of project in the above problem is 13 days 9 days 19 days 14 days 13 days 9 days 19 days 14 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawler-mounted and pneumatic tyre-mounted machines would be respectively 80 and 90 90 and 80 85 and 75 75 and 83 80 and 90 90 and 80 85 and 75 75 and 83 ANSWER DOWNLOAD EXAMIANS APP