Construction Planning and Management Which of the following surfaces will give highest rolling resistance for a rubber tyred vehicle? Asphalt Firm earth Loose sand Concrete Asphalt Firm earth Loose sand Concrete ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Slack time refers to Both event and activity None of these An event An activity Both event and activity None of these An event An activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In India, are prefabricated components costlier than those of traditional cast-in-situ items that the prefabricated components replace? No, because of repetitive manufacture of a number of elements Yes, because of heavier overheads and handling cost No, because of savings in site labour Yes, because of the very high order of quality control for the factory made components No, because of repetitive manufacture of a number of elements Yes, because of heavier overheads and handling cost No, because of savings in site labour Yes, because of the very high order of quality control for the factory made components ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following surfaces will give highest coefficient of traction while using crawler track tractors? Earth Loose sand Concrete Ice Earth Loose sand Concrete Ice ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the critical path method of construction planning, Free Float can be.1. Greater than Total Float.2. Greater than Independent Float3. Equal to Total Float.4. Less than Independent Float 1 and 4 are correct 1 and 4 are correct 2 and 3 are correct 1 and 2 are correct 1 and 4 are correct 1 and 4 are correct 2 and 3 are correct 1 and 2 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Total float for any activity is defined as the difference between Its latest start time and earliest start time Its earliest finish time and earliest start time for its successor activity Its latest start time and earliest finish time Its latest finish time and earliest start time for its successor activity Its latest start time and earliest start time Its earliest finish time and earliest start time for its successor activity Its latest start time and earliest finish time Its latest finish time and earliest start time for its successor activity ANSWER DOWNLOAD EXAMIANS APP