Construction Planning and Management
If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is

500 cum
1000 cum
1500 cum
2000 cum

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Mobilization advance up to 10% of the cost of work is given to a contractor

For all activities required to start the work at site on finalization of the contract document
For the purchase of construction materials
For the payment of advances to labour and other staff
On commencement of work at site for payment of loan taken by him

ANSWER DOWNLOAD EXAMIANS APP