Construction Planning and Management In resources levelling Total duration of project is reduced Cost of project is controlled Uniform demand of resources is achieved Total duration of project is increased Total duration of project is reduced Cost of project is controlled Uniform demand of resources is achieved Total duration of project is increased ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A contractor has two options;(l) : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he could invest in either of the two projects should invest in project A should invest in project B should invest in neither of the two projects could invest in either of the two projects should invest in project A should invest in project B should invest in neither of the two projects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Economic saving of time results by crashing Costliest critical activity Costliest noncritical activity Cheapest critical activity Cheapest noncritical activity Costliest critical activity Costliest noncritical activity Cheapest critical activity Cheapest noncritical activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A golden rule for the procurement of construction stones, suggests 33% at the site and 67% under procurement 67% at the site and 33% under procurement 50% at the site and 50% under procurement 100% at the site 33% at the site and 67% under procurement 67% at the site and 33% under procurement 50% at the site and 50% under procurement 100% at the site ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Construction team means An engineer An architect All listed here An owner An engineer An architect All listed here An owner ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A tractor whose weight is 20 tonnes has a drawbar pull of 2500 kg, when operated on a level road having a rolling resistance of 30 kg per tonne. If this tractor is operated on a level road having a rolling resistance of 40 kg per tonne, then the drawbar pull of the tractor will Reduce by 250 kg Increase by 250 kg Reduce by 200 kg Increase by 200 kg Reduce by 250 kg Increase by 250 kg Reduce by 200 kg Increase by 200 kg ANSWER DOWNLOAD EXAMIANS APP