Construction Planning and Management In resources levelling Total duration of project is reduced Cost of project is controlled Total duration of project is increased Uniform demand of resources is achieved Total duration of project is reduced Cost of project is controlled Total duration of project is increased Uniform demand of resources is achieved ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The direct cost of a project with respect to normal time is Zero Minimum Maximum Infinite Zero Minimum Maximum Infinite ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A tractor whose weight is 20 tonnes has a drawbar pull of 2500 kg, when operated on a level road having a rolling resistance of 30 kg per tonne. If this tractor is operated on a level road having a rolling resistance of 40 kg per tonne, then the drawbar pull of the tractor will Reduce by 250 kg Increase by 200 kg Reduce by 200 kg Increase by 250 kg Reduce by 250 kg Increase by 200 kg Reduce by 200 kg Increase by 250 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as Free float Independent float Interfering float Total float Free float Independent float Interfering float Total float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The area under the Beta distribution curve is divided into two equal parts by Optimistic time Expected time Pessimistic time Most likely time Optimistic time Expected time Pessimistic time Most likely time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For which of the following materials, the output of power shovels for a fixed shovel size will be maximum Moist loam Well blasted rock Good common earth Wet sticky clay Moist loam Well blasted rock Good common earth Wet sticky clay ANSWER DOWNLOAD EXAMIANS APP