Construction Planning and Management
In resources levelling

Cost of project is controlled
Uniform demand of resources is achieved
Total duration of project is reduced
Total duration of project is increased

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Total float for any activity is defined as the difference between

Its latest start time and earliest finish time
Its latest finish time and earliest start time for its successor activity
Its latest start time and earliest start time
Its earliest finish time and earliest start time for its successor activity