Construction Planning and Management

Construction Planning and Management
The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as

Interfering float
Independent float
Free float
Total float

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
The time corresponding to minimum total project cost is

Optimistic time
Between normal time and crash time
Crash time
Normal time

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
The normal time required for the completion of project in the above problem is

13 days
19 days
9 days
14 days

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is

4 days
16 days
10 days
6 days

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
The object of technical planning, is

Preparation of estimates
Initiating the procurement action of resources
Preparation of specifications
All listed here

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
For the execution of a project, a contractor is

An agency
All listed here
A person
A firm

ANSWER DOWNLOAD EXAMIANS APP
MORE MCQ ON Construction Planning and Management

DOWNLOAD APP

  • APPLE
    from app store
  • ANDROID
    from play store

SEARCH

LOGIN HERE


  • GOOGLE

FIND US

  • 1.70K
    FOLLOW US
  • EXAMIANSSTUDY FOR YOUR DREAMS.
  • SUPPORT :SUPPORT EMAIL ACCOUNT : examians@yahoo.com

OTHER WEBSITES

  • GUJARATI MCQ
  • ACCOUNTIANS

QUICK LINKS

  • HOME
  • QUIZ
  • PRIVACY POLICY
  • DISCLAIMER
  • TERMS & CONDITIONS
  • CONTACT US
↑