Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Event Constraint Float Duration Event Constraint Float Duration ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In resources levelling Total duration of project is increased Uniform demand of resources is achieved Total duration of project is reduced Cost of project is controlled Total duration of project is increased Uniform demand of resources is achieved Total duration of project is reduced Cost of project is controlled ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The critical activity has Zero float Maximum float Minimum float None of these Zero float Maximum float Minimum float None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time corresponding to minimum total project cost is Between normal time and crash time Normal time Optimistic time Crash time Between normal time and crash time Normal time Optimistic time Crash time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The normal time required for the completion of project in the above problem is 14 days 19 days 9 days 13 days 14 days 19 days 9 days 13 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Pick up the PERT event from the following: Laying of concrete started Digging of foundation started All listed here Digging of foundation completed Laying of concrete started Digging of foundation started All listed here Digging of foundation completed ANSWER DOWNLOAD EXAMIANS APP