Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Duration Event Constraint Float Duration Event Constraint Float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations:1. Drilling2. Blasting3. Mucking4. Placing steel5. Placing concreteThe correct sequence of these operations in tunnel construction is 1, 2, 3, 4, 5 1, 2, 4, 3, 5 1, 3, 2, 4, 5 1, 3, 4, 2, 5 1, 2, 3, 4, 5 1, 2, 4, 3, 5 1, 3, 2, 4, 5 1, 3, 4, 2, 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the network shown in the given figure, the expected time for the activity All listed here 3-4 is 8 1-2 is 4 2-3 is 7 All listed here 3-4 is 8 1-2 is 4 2-3 is 7 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Mobilization advance up to 10% of the cost of work is given to a contractor For the payment of advances to labour and other staff On commencement of work at site for payment of loan taken by him For the purchase of construction materials For all activities required to start the work at site on finalization of the contract document For the payment of advances to labour and other staff On commencement of work at site for payment of loan taken by him For the purchase of construction materials For all activities required to start the work at site on finalization of the contract document ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For excavating utility trenches with precise control of depth, the excavation equipment used is None of these Shovel Dragline Hoe None of these Shovel Dragline Hoe ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The independent float affects only The particular activity involved None of these Preceding activities Succeeding activities The particular activity involved None of these Preceding activities Succeeding activities ANSWER DOWNLOAD EXAMIANS APP