Construction Planning and Management In the given figure, the network of a project represents Activity of an excavation which starts at event No. 1 and ends at even No. 2 Activity of excavation which takes 8 units of time Activity of an excavation of a footing None of these Activity of an excavation which starts at event No. 1 and ends at even No. 2 Activity of excavation which takes 8 units of time Activity of an excavation of a footing None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The object of technical planning, is Initiating the procurement action of resources All listed here Preparation of specifications Preparation of estimates Initiating the procurement action of resources All listed here Preparation of specifications Preparation of estimates ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Crash project duration is obtained by summing the Crash durations for all activities Normal durations for all the activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Crash durations for all activities Normal durations for all the activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is 6 days 16 days 4 days 10 days 6 days 16 days 4 days 10 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Wheeled tractors are replacing crawler tractors because1. Wheeled tractors travel faster.2. Crawler tractors are more expensive.3. Track parts of a crawler wear out quickly.4. Crawler tractors have stick control.of following statements 2, 3 and 4 are correct 1, 2 and 4 are correct 1, 2 and 3 are correct 1, 3 and 4 are correct 2, 3 and 4 are correct 1, 2 and 4 are correct 1, 2 and 3 are correct 1, 3 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements for a power shovel: (i) Output can be increased by reducing the angle of swing for a given depth of cut. (ii) For a given angle of swing, output will be maximum at optimum depth of cut. (iii) Output can be increased by keeping the depth of cut less than optimum depth. (iv) Output can be increased by increasing the size of shovel. (i), (ii) and (iv) are correct (ii), (iii) and (iv) are correct (i), (iii) and (iv) are correct (i) and (iv) are correct (i), (ii) and (iv) are correct (ii), (iii) and (iv) are correct (i), (iii) and (iv) are correct (i) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP