Construction Planning and Management
Mobilization advance up to 10% of the cost of work is given to a contractor

For the payment of advances to labour and other staff
For all activities required to start the work at site on finalization of the contract document
On commencement of work at site for payment of loan taken by him
For the purchase of construction materials

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
The reduction in project time normally results in

Increasing the direct cost and decreasing the indirect cost
Decreasing the direct cost and indirect cost both
Increasing the direct cost and indirect cost both
Decreasing the direct cost and increasing indirect cost

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Pick up the correct statement from the following with regards to C.P.M. network analysis of projects

Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity
All listed here
The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time
The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time

ANSWER DOWNLOAD EXAMIANS APP