Construction Planning and Management Mobilization advance up to 10% of the cost of work is given to a contractor For the payment of advances to labour and other staff For all activities required to start the work at site on finalization of the contract document On commencement of work at site for payment of loan taken by him For the purchase of construction materials For the payment of advances to labour and other staff For all activities required to start the work at site on finalization of the contract document On commencement of work at site for payment of loan taken by him For the purchase of construction materials ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Pick up the PERT event from the following: Digging of foundation started All listed here Laying of concrete started Digging of foundation completed Digging of foundation started All listed here Laying of concrete started Digging of foundation completed ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The maximum rimpull in the first gear of a tractor while towing a load is 6300 kg. The tractor weighs 12.5 tonnes and is operating along a 2 percent upgrade and the rolling resistance is 45 kg/tonne. Pull available for towing the load is 5515 kg 2975 kg 4350 kg 3425 kg 5515 kg 2975 kg 4350 kg 3425 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the critical path method of construction planning, Free Float can be.1. Greater than Total Float.2. Greater than Independent Float3. Equal to Total Float.4. Less than Independent Float 1 and 4 are correct 1 and 4 are correct 2 and 3 are correct 1 and 2 are correct 1 and 4 are correct 1 and 4 are correct 2 and 3 are correct 1 and 2 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Mile Stone charts were invented in the year of 1920 1930 1940 1910 1920 1930 1940 1910 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A golden rule for the procurement of construction stones, suggests 67% at the site and 33% under procurement 33% at the site and 67% under procurement 100% at the site 50% at the site and 50% under procurement 67% at the site and 33% under procurement 33% at the site and 67% under procurement 100% at the site 50% at the site and 50% under procurement ANSWER DOWNLOAD EXAMIANS APP