The critical activity has

None of these
Maximum float
Zero float
Minimum float

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
While scheduling a project by C.P.M.

Required time for each activity is established
Net work is drawn by connecting the activities and the events
A project is divided into various activities
All listed here

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
The difference between the time avail-to do a job and the time required to do the job, is known as

Event
Float
Constraint
Duration

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Sensitivity analysis is a study of

Comparison of assets and liabilities
Economics of cost and benefits of the project
Change in output due to change in input
Comparison of profit and loss

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Which of the following is a weakness of bar chart?

Project progress
Interdependencies of activities
All of these
Uncertainties

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
The main disadvantage of line organization, is

Extraordinary delay in communications
All listed here
Top level executions over work
Rigid structure

ANSWER DOWNLOAD EXAMIANS APP
MORE MCQ ON Construction Planning and Management

DOWNLOAD APP

  • APPLE
    from app store
  • ANDROID
    from play store

SEARCH

LOGIN HERE


  • GOOGLE

FIND US

  • 1.70K
    FOLLOW US
  • EXAMIANSSTUDY FOR YOUR DREAMS.
  • SUPPORT :SUPPORT EMAIL ACCOUNT : examians@yahoo.com

OTHER WEBSITES

  • GUJARATI MCQ
  • ACCOUNTIANS

QUICK LINKS

  • HOME
  • QUIZ
  • PRIVACY POLICY
  • DISCLAIMER
  • TERMS & CONDITIONS
  • CONTACT US
↑