Construction Planning and Management
Preliminary project report for a road project must contain

The soil survey, traffic survey, concept design and approximate cost
The several alternatives of the project that have been considered
The detailed estimated cost based on detailed design
The contract documents for inviting tenders

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
A contractor has two options;(l) : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he

should invest in project B
should invest in neither of the two projects
could invest in either of the two projects
should invest in project A

ANSWER DOWNLOAD EXAMIANS APP