Estimating and Costing Size, capacity and materials need be specified for Bib-cocks Stop-cocks All of these Ball valves Bib-cocks Stop-cocks All of these Ball valves ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of half brick partition wall per mason per day is 1.5 m2 5.0 m2 2.0 m2 4.0 m2 1.5 m2 5.0 m2 2.0 m2 4.0 m2 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is 0.94 m³ 0.98 m³ 1.00 m³ 0.90 m³ 0.94 m³ 0.98 m³ 1.00 m³ 0.90 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The following item of earth work is not measured separately. All listed here Setting out of works Site clearance Steps in deep excavation All listed here Setting out of works Site clearance Steps in deep excavation ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length. The height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by Prismoidal formula, is 3250 m³ 3300 m³ 3225 m³ 3275 m³ 3250 m³ 3300 m³ 3225 m³ 3275 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The reduced levels of points, 30 metres apart along the longitudinal section of a road portion between chainages 5 and 9 are shown in the given figure. If there is a uniform up-gradient of the road 120 in 1, the chainage of the point with no filling or cutting is None of these (6 + 15) chains (6 + 18) chains (6 + 12) chains None of these (6 + 15) chains (6 + 18) chains (6 + 12) chains ANSWER DOWNLOAD EXAMIANS APP