Construction Planning and Management Latest start of an activity is always greater than or equal to latest event time of preceding node equal to latest event time of preceding node less than latest event time of preceding node less than or equal to latest event time of preceding node greater than or equal to latest event time of preceding node equal to latest event time of preceding node less than latest event time of preceding node less than or equal to latest event time of preceding node ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Frequency distribution curves All listed here Having a single lump, are called uninodal curves If symmetrical, are called normal curves If not symmetrical, are called skew curves All listed here Having a single lump, are called uninodal curves If symmetrical, are called normal curves If not symmetrical, are called skew curves ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is 4 days 16 days 10 days 6 days 4 days 16 days 10 days 6 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion (A): Activity 57 is critical.Reason (R): Earliest finish time and latest finish time for events 57 are same A is correct but R is not correct Both A and R is correct R is correct but A is not correct Both A and R is incorrect A is correct but R is not correct Both A and R is correct R is correct but A is not correct Both A and R is incorrect ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A tractor shovel has a purchase price of Rs. 4.7 lacs and could save the organization an amount of rupees one lac per year on operating costs. The salvage value after the amortization period is 10% of the purchase price. The capital recovery period will be 7.87 years 3.7 years 5 years 4.23 years 7.87 years 3.7 years 5 years 4.23 years ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be Started 5 days later All listed here Completed 5 days later Performed at slower rate in 15 days Started 5 days later All listed here Completed 5 days later Performed at slower rate in 15 days ANSWER DOWNLOAD EXAMIANS APP