Estimating and Costing The plinth area of a building not includes Internal shaft for sanitary installations up to 2 sq m. in area Lift and wall including landing Area of the walls at the floor level Area of cantilevered porch Internal shaft for sanitary installations up to 2 sq m. in area Lift and wall including landing Area of the walls at the floor level Area of cantilevered porch ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing In the mid-section formula The area of mid-sections is calculated by using mean depth All of these The mean depth is the average of depths of two consecutive sections The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections The area of mid-sections is calculated by using mean depth All of these The mean depth is the average of depths of two consecutive sections The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The inspection pit or chamber is a manhole provided in a base drainage system All of these At every change of direction At every 30 m intervals At every change of gradient All of these At every change of direction At every 30 m intervals At every change of gradient ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Anti-siphonage pipe is connected to Bottom of P trap W.C. Main soil pipe Side of water closet Top of P trap W.C. Bottom of P trap W.C. Main soil pipe Side of water closet Top of P trap W.C. ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The 'centre line method' is specially adopted for estimating Hexagonal buildings Circular buildings All of these Octagonal buildings Hexagonal buildings Circular buildings All of these Octagonal buildings ANSWER DOWNLOAD EXAMIANS APP