Estimating and Costing

Estimating and Costing
Anti-siphonage pipe is connected to

Side of water closet
Bottom of P trap W.C.
Top of P trap W.C.
Main soil pipe

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
The measurement is made in square metre in case of

R.C.C. structure
None of these
Cement concrete in foundation
Hollow concrete block wall

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
A portion of an embankment having a uniform up-gradient 1 in 500 is circular with radius 1000 m of the centre line. It subtends 180° at the centre. If the height of the bank is 1 m at the lower end, and side slopes 2:1, the earth work involved.

26,000 m³
27,000 m³
26,500 m³
27,500 m³

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is

1.75 m³
1.50 m³
1.25 m³
1.00 m³

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
The item of steel work which is measured in sq.m, is

All listed here
Collapsible gates
Ventilators and glazing
Rolling shutters

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
The item of the brick structure measured in sq.m, is

Brick work in arches
Broken glass coping
Brick edging
Reinforced brick work

ANSWER DOWNLOAD EXAMIANS APP
MORE MCQ ON Estimating and Costing

DOWNLOAD APP

  • APPLE
    from app store
  • ANDROID
    from play store

SEARCH

LOGIN HERE


  • GOOGLE

FIND US

  • 1.70K
    FOLLOW US
  • EXAMIANSSTUDY FOR YOUR DREAMS.
  • SUPPORT :SUPPORT EMAIL ACCOUNT : examians@yahoo.com

OTHER WEBSITES

  • GUJARATI MCQ
  • ACCOUNTIANS

QUICK LINKS

  • HOME
  • QUIZ
  • PRIVACY POLICY
  • DISCLAIMER
  • TERMS & CONDITIONS
  • CONTACT US
↑