Construction Planning and Management CPM is Is built of activities oriented programme All listed here Synthesising in concepts Is based on time estimate Is built of activities oriented programme All listed here Synthesising in concepts Is based on time estimate ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is 2 1 4 3 2 1 4 3 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time with which direct cost does not reduce with the increase in time is known as Standard time Optimistic time Normal time Crash time Standard time Optimistic time Normal time Crash time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The normal time required for the completion of project in the above problem is 9 days 14 days 19 days 13 days 9 days 14 days 19 days 13 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively 4 and 5/6 3.5 and 5/6 3.5 and 25/36 5 and 25/36 4 and 5/6 3.5 and 5/6 3.5 and 25/36 5 and 25/36 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 8 days 15 days 9 days 10 days 8 days 15 days 9 days 10 days ANSWER DOWNLOAD EXAMIANS APP