Construction Planning and Management Critical path lies along the activities having total float Positive Same Negative Zero Positive Same Negative Zero ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Event Duration Constraint Float Event Duration Constraint Float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A father notes that when his teenage daughter uses the telephone, she takes not less than 6 minutes for a call and som? times as much as an hour. Fifteen minutes call are more frequent than calls of any other duration. If these phone calls were an activity in PERT project, then phone calls expected duration will be 20.143 minutes 27 minutes 21 minutes 15 minutes 20.143 minutes 27 minutes 21 minutes 15 minutes ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as Free float Independent float Total float Interfering float Free float Independent float Total float Interfering float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Final technical authority of a project lies with Assistant Engineer Chief Engineer Executive Engineer Superintending Engineer Assistant Engineer Chief Engineer Executive Engineer Superintending Engineer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The object of technical planning, is All listed here Preparation of estimates Preparation of specifications Initiating the procurement action of resources All listed here Preparation of estimates Preparation of specifications Initiating the procurement action of resources ANSWER DOWNLOAD EXAMIANS APP