Construction Planning and Management Critical path lies along the activities having total float Negative Zero Positive Same Negative Zero Positive Same ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Mobilization advance up to 10% of the cost of work is given to a contractor On commencement of work at site for payment of loan taken by him For all activities required to start the work at site on finalization of the contract document For the purchase of construction materials For the payment of advances to labour and other staff On commencement of work at site for payment of loan taken by him For all activities required to start the work at site on finalization of the contract document For the purchase of construction materials For the payment of advances to labour and other staff ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following surfaces will give highest rolling resistance for a rubber tyred vehicle? Firm earth Concrete Loose sand Asphalt Firm earth Concrete Loose sand Asphalt ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The first method invented for planning projects, was Programme Evaluation and Review Technique (PERT) Bar chart method Milestone chart Critical path method (CPM) Programme Evaluation and Review Technique (PERT) Bar chart method Milestone chart Critical path method (CPM) ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The salient feature of functional organization is All listed here Separation of planning and design part Strict adherence to specifications Each individual maintains functional efficiency All listed here Separation of planning and design part Strict adherence to specifications Each individual maintains functional efficiency ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Completion of an activity on CPM network diagram, is generally known All listed here Event Node Connector All listed here Event Node Connector ANSWER DOWNLOAD EXAMIANS APP