Construction Planning and Management Critical path lies along the activities having total float Positive Zero Negative Same Positive Zero Negative Same ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The area under the Beta distribution curve is divided into two equal parts by Expected time Most likely time Optimistic time Pessimistic time Expected time Most likely time Optimistic time Pessimistic time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Economic saving of time results by crashing Cheapest critical activity Costliest critical activity Costliest noncritical activity Cheapest noncritical activity Cheapest critical activity Costliest critical activity Costliest noncritical activity Cheapest noncritical activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the critical path method of construction planning, Free Float can be.1. Greater than Total Float.2. Greater than Independent Float3. Equal to Total Float.4. Less than Independent Float 2 and 3 are correct 1 and 2 are correct 1 and 4 are correct 1 and 4 are correct 2 and 3 are correct 1 and 2 are correct 1 and 4 are correct 1 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The salient feature of functional organization is All listed here Separation of planning and design part Strict adherence to specifications Each individual maintains functional efficiency All listed here Separation of planning and design part Strict adherence to specifications Each individual maintains functional efficiency ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having Shortest duration Highest cost slope Longest duration Least cost slope Shortest duration Highest cost slope Longest duration Least cost slope ANSWER DOWNLOAD EXAMIANS APP