Construction Planning and Management Batching refers to Controlling the total quantity at each batch Controlling the quantity of each material into each batch Adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch Weighing accurately, the quantity of each material for a job before mixing Controlling the total quantity at each batch Controlling the quantity of each material into each batch Adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch Weighing accurately, the quantity of each material for a job before mixing ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Military organization is known as Line and staff organization Functional organization None of these Line organization Line and staff organization Functional organization None of these Line organization ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path lies along the activities having total float Same Negative Zero Positive Same Negative Zero Positive ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management An excavator costs Rs. 20,00,000 and has an estimated life of 8 years. It has no salvage value at the end of 8 years. The book value of the excavator at the end of 3 years using general double declining balance method is Rs. 8,75,000 Rs. 8,43,750 Rs. 10,50,000 Rs. 11,56,250 Rs. 8,75,000 Rs. 8,43,750 Rs. 10,50,000 Rs. 11,56,250 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Slack time refers to Both event and activity An activity An event None of these Both event and activity An activity An event None of these ANSWER DOWNLOAD EXAMIANS APP