Construction Planning and Management Preliminary project report for a road project must contain The soil survey, traffic survey, concept design and approximate cost The contract documents for inviting tenders The detailed estimated cost based on detailed design The several alternatives of the project that have been considered The soil survey, traffic survey, concept design and approximate cost The contract documents for inviting tenders The detailed estimated cost based on detailed design The several alternatives of the project that have been considered ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations: 1. Drilling 2. Blasting 3. Mucking 4. Placing steel 5. Placing concrete The correct sequence of these operations in tunnel construction is 1, 3, 2, 4, 5 1, 3, 4, 2, 5 1, 2, 3, 4, 5 1, 2, 4, 3, 5 1, 3, 2, 4, 5 1, 3, 4, 2, 5 1, 2, 3, 4, 5 1, 2, 4, 3, 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The salient feature of functional organization is Strict adherence to specifications Each individual maintains functional efficiency Separation of planning and design part All listed here Strict adherence to specifications Each individual maintains functional efficiency Separation of planning and design part All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time corresponding to minimum total project cost is Between normal time and crash time Crash time Optimistic time Normal time Between normal time and crash time Crash time Optimistic time Normal time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The process of incorporating changes and rescheduling or replanning is called Resource levelling Critical path scheduling Updating Resource smoothening Resource levelling Critical path scheduling Updating Resource smoothening ANSWER DOWNLOAD EXAMIANS APP