Construction Planning and Management The time corresponding to minimum total project cost is Between normal time and crash time Optimistic time Crash time Normal time Between normal time and crash time Optimistic time Crash time Normal time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 500 cum 1500 cum 2000 cum 1000 cum 500 cum 1500 cum 2000 cum 1000 cum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Updating may result in All of these Increase of project completion time Change of critical path Decrease of project completion time All of these Increase of project completion time Change of critical path Decrease of project completion time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Pick up the PERT event from the following: Laying of concrete started Digging of foundation completed All listed here Digging of foundation started Laying of concrete started Digging of foundation completed All listed here Digging of foundation started ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Latest start of an activity is always less than latest event time of preceding node greater than or equal to latest event time of preceding node equal to latest event time of preceding node less than or equal to latest event time of preceding node less than latest event time of preceding node greater than or equal to latest event time of preceding node equal to latest event time of preceding node less than or equal to latest event time of preceding node ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements for a power shovel:(i) Output can be increased by reducing the angle of swing for a given depth of cut.(ii) For a given angle of swing, output will be maximum at optimum depth of cut.(iii) Output can be increased by keeping the depth of cut less than optimum depth.(iv) Output can be increased by increasing the size of shovel. (ii), (iii) and (iv) are correct (i), (ii) and (iv) are correct (i) and (iv) are correct (i), (iii) and (iv) are correct (ii), (iii) and (iv) are correct (i), (ii) and (iv) are correct (i) and (iv) are correct (i), (iii) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP