Construction Planning and Management The process of incorporating changes and rescheduling or replanning is called Critical path scheduling Updating Resource smoothening Resource levelling Critical path scheduling Updating Resource smoothening Resource levelling ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A CPM family includes CPA (Critical Path Analysis) CPP (Critical Path Plotted) MCE (Minimum Cost Expenditure) All listed here CPA (Critical Path Analysis) CPP (Critical Path Plotted) MCE (Minimum Cost Expenditure) All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following represents an activity? All listed here Excavation for foundation Setting of question paper Curing of concrete All listed here Excavation for foundation Setting of question paper Curing of concrete ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good EF = ES + D LF = LS + D All listed here LS = LF - D EF = ES + D LF = LS + D All listed here LS = LF - D ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Free float is mainly used to Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities Identify the activities which can be delayed without affecting the total float of preceding activity Identify the activities, which can be delayed without affecting the total float of succeeding activity Establish priorities Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities Identify the activities which can be delayed without affecting the total float of preceding activity Identify the activities, which can be delayed without affecting the total float of succeeding activity Establish priorities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be 97.7% and 84.1% 15.9% and 97.7% 97.7 % and 15.9% 2.3% and 84.1% 97.7% and 84.1% 15.9% and 97.7% 97.7 % and 15.9% 2.3% and 84.1% ANSWER DOWNLOAD EXAMIANS APP