Construction Planning and Management
Total float for any activity is defined as the difference between

Its latest start time and earliest start time
Its earliest finish time and earliest start time for its successor activity
Its latest start time and earliest finish time
Its latest finish time and earliest start time for its successor activity

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Sinking fund is

Raised to meet maintenance costs
A part of the money kept in reserve for providing additional structures and structural modifications
The total sum to be paid to the municipal authorities by the tenants
The fund for rebuilding a structure when its economic life is over

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Preliminary project report for a road project must contain

The several alternatives of the project that have been considered
The detailed estimated cost based on detailed design
The contract documents for inviting tenders
The soil survey, traffic survey, concept design and approximate cost

ANSWER DOWNLOAD EXAMIANS APP