Consider the following surveys. 1. Reconnaissance survey 2. Preliminary survey 3. Traffic survey 4. Location survey The correct sequence in which these surveys are conducted before the alignment of a track is finalised is

1,3,4,2
3,1,4,2
1,3,2,4
3,1,2,4