Railway Engineering Consider the following surveys. 1. Reconnaissance survey 2. Preliminary survey 3. Traffic survey 4. Location survey The correct sequence in which these surveys are conducted before the alignment of a track is finalised is 3,1,4,2 1,3,4,2 1,3,2,4 3,1,2,4 3,1,4,2 1,3,4,2 1,3,2,4 3,1,2,4 ANSWER DOWNLOAD EXAMIANS APP
Railway Engineering The object of providing a point lock is to ensure that each switch is correctly set None of these to detect any obstruction between and tongue rail to ensure that the point may not be operated while the train is on it to ensure that each switch is correctly set None of these to detect any obstruction between and tongue rail to ensure that the point may not be operated while the train is on it ANSWER DOWNLOAD EXAMIANS APP
Railway Engineering The desirable rate of change of cant deficiency in case of Metre Gauge is 20 mm/sec 55 mm/sec 65 mm/sec 35 mm/sec 20 mm/sec 55 mm/sec 65 mm/sec 35 mm/sec ANSWER DOWNLOAD EXAMIANS APP
Railway Engineering Number offish bolts per fish plate is 6 5 4 2 6 5 4 2 ANSWER DOWNLOAD EXAMIANS APP
Railway Engineering A train is hauled by 2-8-2 locomotive with 22.5 tonnes and on each driving axle. Assuming the coefficient of rail-wheel friction to be 0.25, what would be the hauling capacity of the locomotive? 45.0 tonnes 15.0 tonnes 22.5 tonnes 90.0 tonnes 45.0 tonnes 15.0 tonnes 22.5 tonnes 90.0 tonnes ANSWER DOWNLOAD EXAMIANS APP
Railway Engineering The standard length of rail for Broad Gauge and Meter Gauge are respectively 12 m and 13 m 13 m and 12 m 12 m and 12 m 13 m and 13 m 12 m and 13 m 13 m and 12 m 12 m and 12 m 13 m and 13 m ANSWER DOWNLOAD EXAMIANS APP