Building Construction The maximum permissible differential settlement, in case of foundations in clayey soil, is usually limited to 40 mm 20 mm 30 mm 10 mm 40 mm 20 mm 30 mm 10 mm ANSWER DOWNLOAD EXAMIANS APP
Building Construction The taper of precast concrete pile should not be more than 2 cm per metre length 1 cm per metre length 5 cm per metre length 4 cm per metre length 2 cm per metre length 1 cm per metre length 5 cm per metre length 4 cm per metre length ANSWER DOWNLOAD EXAMIANS APP
Building Construction The process of making the back ground rough, before plastering, is Peeling Hacking Blistering Dubbing Peeling Hacking Blistering Dubbing ANSWER DOWNLOAD EXAMIANS APP
Building Construction Which one of the following activities is not correct as applicable to brick corbels The discontinuous corbels are used to carry heavy concentrated loads Stretcher bond is generally used for the construction of brick corbel The maximum projection of each corbel course should be limited to a quarter brick at a time The maximum projection of the corbel should not be more than the thickness of the wall The discontinuous corbels are used to carry heavy concentrated loads Stretcher bond is generally used for the construction of brick corbel The maximum projection of each corbel course should be limited to a quarter brick at a time The maximum projection of the corbel should not be more than the thickness of the wall ANSWER DOWNLOAD EXAMIANS APP
Building Construction Exposed portions of vertical surface at right angles to the door or window frame, are known as Soffits Jambs Reveals Lintels Soffits Jambs Reveals Lintels ANSWER DOWNLOAD EXAMIANS APP
Building Construction The ceiling height of a building is Between ceiling and ground level Upto roof above ground level Between ceiling and floor level Upto ceiling from the ground level Between ceiling and ground level Upto roof above ground level Between ceiling and floor level Upto ceiling from the ground level ANSWER DOWNLOAD EXAMIANS APP