Estimating and Costing The floor area includes the area of the balcony up to 0.75 1 0.25 0.5 0.75 1 0.25 0.5 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing A portion of an embankment having a uniform up-gradient 1 in 500 is circular with radius 1000 m of the centre line. It subtends 180° at the centre. If the height of the bank is 1 m at the lower end, and side slopes 2:1, the earth work involved. 26,500 m³ 27,500 m³ 27,000 m³ 26,000 m³ 26,500 m³ 27,500 m³ 27,000 m³ 26,000 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing If tensile stress of a steel rod of diameter ‘D’ is 1400 kg/cm² and bond stress is 6 kg/cm², the required bond length of the rod is 59 D 50 D 39 D 30 D 59 D 50 D 39 D 30 D ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Referring of given figure, pick up the correct statement from the following: The total length of centre line of four walls is 20 m Length of long wall out-to-out is 6.80 m All listed here Length of short walls in-to-in is 3.20 m The total length of centre line of four walls is 20 m Length of long wall out-to-out is 6.80 m All listed here Length of short walls in-to-in is 3.20 m ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing While preparing a detailed estimate Volume should be measured correct to 0.01 cum Area should be measured correct to 0.01 sqm All of these Dimension should be measured correct to 0.01 m Volume should be measured correct to 0.01 cum Area should be measured correct to 0.01 sqm All of these Dimension should be measured correct to 0.01 m ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The following item of earth work is not measured separately. Steps in deep excavation All listed here Setting out of works Site clearance Steps in deep excavation All listed here Setting out of works Site clearance ANSWER DOWNLOAD EXAMIANS APP