Industrial Engineering and Production Management The time which results in the least possible direct cost of an activity is known as Crash time Standard time Normal time Slow time Crash time Standard time Normal time Slow time ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management When slack of an activity is negative It represents a situation where extra resources are available and the completion of project is not delayed The activity is critical and any delay in its performance will delay the completion of whole project All of these It represents that a programme falls behind schedule and additional resources are required to complete the project in time It represents a situation where extra resources are available and the completion of project is not delayed The activity is critical and any delay in its performance will delay the completion of whole project All of these It represents that a programme falls behind schedule and additional resources are required to complete the project in time ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management When slack of an activity is positive The activity is critical and any delay in its performance will delay the completion of whole project Any one of the above It represents a situation where extra resources are available and the completion of project is not delayed It represents that a programme falls behind schedule and additional resources are required to complete the project in time The activity is critical and any delay in its performance will delay the completion of whole project Any one of the above It represents a situation where extra resources are available and the completion of project is not delayed It represents that a programme falls behind schedule and additional resources are required to complete the project in time ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management If TL is the largest allowable event occurrence time, total activity slack (s) is equal to All of these Latest start time earliest start time TLEFT Latest finish time earliest finish time (EFT) All of these Latest start time earliest start time TLEFT Latest finish time earliest finish time (EFT) ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Tick the odd man out Taylor McGregor Drucker Galileo Taylor McGregor Drucker Galileo ANSWER DOWNLOAD EXAMIANS APP