Industrial Engineering and Production Management Scheduling gives information about When work should complete When work should start and how much work should be completed during a certain period Proper utilization of machines That how idle time can be minimized When work should complete When work should start and how much work should be completed during a certain period Proper utilization of machines That how idle time can be minimized ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management In PERT analysis, critical path is obtained by joining events having -ve slack Zero slack Dummy activities +ve slack -ve slack Zero slack Dummy activities +ve slack ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management CPM has following time estimate One time estimate Three time estimate Two time estimate Four time estimate One time estimate Three time estimate Two time estimate Four time estimate ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management PERT has following time estimate Three time estimate One time estimate Two time estimate Four time estimate Three time estimate One time estimate Two time estimate Four time estimate ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The routing function in a production system design is concerned with Machine utilization Optimizing material flow through the plant Manpower utilization Quality assurance of the product Machine utilization Optimizing material flow through the plant Manpower utilization Quality assurance of the product ANSWER DOWNLOAD EXAMIANS APP