The assumption in PERT is

Cost of project will always be more than the estimated cost, if no timely corrections are taken
Activities are fixed and can't be changed
A project will always be behind schedule, if left uncorrected
A project can be subdivided into a set of predictable, independent activities

ANSWER DOWNLOAD EXAMIANS APP

Industrial Engineering and Production Management
Which of the following are the guidelines for the construction of a network diagram?

Dangling must be avoided in a network diagram
Dummy activity consumes no time or resource
All of the these
Each activity is represented by one and only one arrow in the network