Industrial Engineering and Production Management
When slack of an activity is positive

It represents a situation where extra resources are available and the completion of project is not delayed
Any one of the above
It represents that a programme falls behind schedule and additional resources are required to complete the project in time
The activity is critical and any delay in its performance will delay the completion of whole project

ANSWER DOWNLOAD EXAMIANS APP

Industrial Engineering and Production Management
A big advantage of PERT over Gantt charts is that in the former case

Activities and events are clearly shown
Activity times are clear
Interrelationship among activities is clearly shown
Early start and late finish of an activity are clearly marked

ANSWER DOWNLOAD EXAMIANS APP