Industrial Engineering and Production Management When slack of an activity is positive Any one of the above It represents that a programme falls behind schedule and additional resources are required to complete the project in time It represents a situation where extra resources are available and the completion of project is not delayed The activity is critical and any delay in its performance will delay the completion of whole project Any one of the above It represents that a programme falls behind schedule and additional resources are required to complete the project in time It represents a situation where extra resources are available and the completion of project is not delayed The activity is critical and any delay in its performance will delay the completion of whole project ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Monte Carlo solutions in queuing theory are extremely useful in queuing problems Involving multistage queuing That can't be analysed mathematically To verify mathematical results All of the these Involving multistage queuing That can't be analysed mathematically To verify mathematical results All of the these ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Activity slack or float of any event on a PERT/CPM chart is represented by Anyone of the above Latest start time of succeeding event earliest finish time of preceding event activity time Latest finish time of event earliest finish time of the event Latest start time of the event earliest start time of the event Anyone of the above Latest start time of succeeding event earliest finish time of preceding event activity time Latest finish time of event earliest finish time of the event Latest start time of the event earliest start time of the event ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The unit cost in case of batch production is __________as compared to jobbing production. Same None of these High Low Same None of these High Low ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Positive slack on a PERT indicates that project is Beyond schedule Ahead of schedule On critical path As per schedule Beyond schedule Ahead of schedule On critical path As per schedule ANSWER DOWNLOAD EXAMIANS APP