Industrial Engineering and Production Management When slack of an activity is positive The activity is critical and any delay in its performance will delay the completion of whole project Any one of the above It represents a situation where extra resources are available and the completion of project is not delayed It represents that a programme falls behind schedule and additional resources are required to complete the project in time The activity is critical and any delay in its performance will delay the completion of whole project Any one of the above It represents a situation where extra resources are available and the completion of project is not delayed It represents that a programme falls behind schedule and additional resources are required to complete the project in time ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management A device used for lifting or lowering objects suspended from a hook at the end of retractable chains or cable is called Chain conveyor Portable elevator Jib crane Hoist Chain conveyor Portable elevator Jib crane Hoist ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The time of completing a project in network analysis is given by following time of the critical activity meeting at the final triode Early start Late start Late finish Early finish Early start Late start Late finish Early finish ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management In PERT analysis, critical path is obtained by joining events having Dummy activities -ve slack +ve slack Zero slack Dummy activities -ve slack +ve slack Zero slack ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Which one of the following chart gives simultaneously information about the progress of work and machine loading? Man-machine chart Gantt chart Process chart Machine load chart Man-machine chart Gantt chart Process chart Machine load chart ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Routing prescribes the Flow of material in the plant Inspection of final product Proper utilization of man power Proper utilization of machines Flow of material in the plant Inspection of final product Proper utilization of man power Proper utilization of machines ANSWER DOWNLOAD EXAMIANS APP