Critical Path Net Work helps an engineer

To concentrate his attention on critical activities
To be cautious for avoiding any delay in the critical activities to avoid delay of the whole project
All of these
To divert the resources from noncritical advanced activities to critical activities

ANSWER DOWNLOAD EXAMIANS APP