Industrial Engineering and Production Management Replacement studies are made on the following basis Annual cost method Total life average method Any one of the above Rate of return method Annual cost method Total life average method Any one of the above Rate of return method ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management A milestone chart None of the these Shows the inter dependences of various jobs Depicts the delay of jobs, if any Points outgoing ahead of schedule of jobs, if any None of the these Shows the inter dependences of various jobs Depicts the delay of jobs, if any Points outgoing ahead of schedule of jobs, if any ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management PERT stands for Program Evaluation and Review Technique Program Estimation and Reporting Technique Process Estimation and Review Technique Planning Estimation and Resulting Technique Program Evaluation and Review Technique Program Estimation and Reporting Technique Process Estimation and Review Technique Planning Estimation and Resulting Technique ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management PERT/CPM, techniques can be used for following applications All of these Research and development Maintenance jobs Once through project All of these Research and development Maintenance jobs Once through project ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management In crash program for a project both direct and indirect costs, increase cost is no criterion direct costs increase and indirect costs decrease indirect costs increase and direct costs decrease both direct and indirect costs, increase cost is no criterion direct costs increase and indirect costs decrease indirect costs increase and direct costs decrease ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Scheduling Prescribes the sequence of operations to be followed Is concerned with starting of processes Determines the programme for the operations Regulates the progress of job through various processes Prescribes the sequence of operations to be followed Is concerned with starting of processes Determines the programme for the operations Regulates the progress of job through various processes ANSWER DOWNLOAD EXAMIANS APP