Building Construction In verandah (corridor) floors outward slope is 1 in 60 1 in 50 1 in 40 1 in 70 1 in 60 1 in 50 1 in 40 1 in 70 ANSWER DOWNLOAD EXAMIANS APP
Building Construction In case of multi-storeyed buildings, the forms to be removed first are Sides of beams and girders All the above at the same time Bottom of beams and girders Column forms Sides of beams and girders All the above at the same time Bottom of beams and girders Column forms ANSWER DOWNLOAD EXAMIANS APP
Building Construction The process of keeping concrete moist for a certain period after its finishing, is known as Compaction of concrete Curing of concrete Placing of concrete Finishing of concrete Compaction of concrete Curing of concrete Placing of concrete Finishing of concrete ANSWER DOWNLOAD EXAMIANS APP
Building Construction The minimum depth of foundation in clayey soils is 1.2 m 0.5 m 0.7 m 0.9 m 1.2 m 0.5 m 0.7 m 0.9 m ANSWER DOWNLOAD EXAMIANS APP
Building Construction The stone whose crushing strength is least, is Chalk Slate Granite Marble Chalk Slate Granite Marble ANSWER DOWNLOAD EXAMIANS APP
Building Construction The method of moving each brick through a small horizontal distance before it is finally laid in any brick wall and pressing it by means of brick hammer, is known as Grouting Laying Placing Troweling Grouting Laying Placing Troweling ANSWER DOWNLOAD EXAMIANS APP